To request water supply for a project, please follow these steps:
STEP 1: APPLICATION DOSSIER PREPARATION AND WATER SUPPLY AGREEMENT
- The Project Owner sends a written request for water supply to BWACO (the document should clearly state the water demand, project location, scale, relevant documents, and project legal dossier, etc.).
- BWACO reviews and responds to the written request and discusses the water supply agreement (if necessary).
STEP 2: CONNECTING THE WATER SUPPLY SYSTEM
1. For projects requiring water supply via a bulk water meter.
- BWACO will install the bulk meter and connect the water supply for the project as requested by the Project Owner. All costs shall be borne by the Project Owner.
- The system downstream of the meter will be managed by the Project Owner.
2. For water supply systems invested by the Project Owner and transferred to BWACO for management.
- The Project Owner implements the water supply system construction according to the technical agreement with BWACO.
- BWACO coordinates the inspection and acceptance of materials and equipment before the Project Owner proceeds with installation.
- BWACO carries out the acceptance and takes over the project’s water supply system.
Note: The customer is NOT required to perform Steps 2 and 3 if the project’s water supply system is constructed by a construction enterprise affiliated with Bà Rịa – Vũng Tàu Water Supply Joint Stock Company.